Sample Foods, light-industrial site, Connecticut
Three buildings: production, packaging hall and a small public room.
What we found, in four lines
- The site's billed peak, about 195 kW around 1 PM, comes from process equipment starting while HVAC and refrigeration are also running.
- Refrigeration is the largest block of energy and never switches off. Overnight the site still draws about 38 kW against a peak near 195 kW.
- Rooftop HVAC starts at 6 AM and runs until 8 PM, so it is on during the billed peak.
- Operations and controls come first. Battery storage and solar come last, sized to the load that is left.
Bill and tariff
The report reads your rate schedule line by line: customer charge, supply, delivery, any time-of-use adder, and the demand charge, which is billed on the highest 30 minutes in the month. It lists which meters the owner pays and which tenants pay.
The load picture above is checked against a month of billed kW and kWh, and any difference is explained.
Where the energy goes
Process equipment about 31% of the day's energy, refrigeration about 35%, HVAC about 24%, plug loads and controls about 8%, lighting about 2%. For each, the report names the equipment, when it runs, and what sets its peak.
Heating and cooling
Equipment age, type and condition, schedules and setpoints, and whether the units can be re-timed or controlled without replacement. Units near end of life are flagged so a replacement can be planned with the other work.
Windows and insulation
Glazing type and orientation, roof and wall insulation, air sealing at doors and roof edges, and where heat is entering or leaving. Findings are ranked by how much they affect HVAC and cold-room load.
ENERGY STAR score, where the building qualifies
Offices, schools, retail, warehouses, hotels, medical offices and multifamily buildings of 20 units or more can receive an EPA ENERGY STAR score from 1 to 100, based on twelve months of energy data for every fuel. Production plants like this sample site are not scored. For a building that qualifies, the report states the score and what would move it.
Recommended measures, in order
| # | Measure | Type | Why |
|---|---|---|---|
| 1 | Move the early-afternoon process start to the morning | Operations | The billed peak at about 1 PM is process equipment starting while HVAC and refrigeration are also running. Shifting that start lowers the peak without buying equipment. |
| 2 | Add controls and variable-speed drives to the chiller and compressor | Retrofit | Refrigeration runs all day and is the largest block of energy. It is the first place to look for a steady saving. |
| 3 | Re-time rooftop HVAC and add economizer controls | Retrofit | Units start at 6 AM and run until 8 PM. Better scheduling and controls cut how much they draw during the billed peak. |
| 4 | Seal and insulate the packaging hall roof edge and loading doors | Building envelope | Infiltration and an under-insulated roof make the HVAC and cold room work harder in summer and winter. |
| 5 | Battery storage to hold the site under a demand target | Storage | A short, high peak is what a battery handles well. Sized only after measures 1 to 4, so it is not oversized. |
| 6 | Rooftop or canopy solar, after the roof is checked | Generation | Sized last, to the load that remains and to the roof's age and structure. |
In your report each measure carries its estimated cost and its effect on your bill, worked on your tariff, plus the incentives open to the building. This sample leaves those figures out because they depend on the real building.
What happens after the report
We help you close the gaps the report finds, from controls and retrofits to storage and solar, in the order that makes sense for the building. If a project does not make sense, the report says so.